The Government of Uzbekistan aims to generate cost-effective and eco-friendly electricity to meet rising demands. With this in mind, JSC "Uzbekhydroenergo" is beginning procurement for the first lot of five new hydropower plants, totaling an estimated 46.6 MW capacity, under a PPP agreement.
The Central Asian country aims to attract foreign investment for hydropower projects by implementing an internationally accepted framework.
Uzbekistan also seeks to establish a positive track record for PPP-based projects, allocate risks fairly, diversify the country's energy generation mix, ensure transparent tender processes, and generate competitive tariffs.
The JSC “Uzbekhydroenergo” seeks private developers or consortia to construct, finance, own, and operate a project during the concession period.
As per the country's Ministry of Energy, interested parties should provide a Statement of Qualification (SOQ) according to the Request for Qualification (RFQ) documents.
To access the RFQ documents, interested individuals must agree to the Non-Disclosure Agreement (NDA) and send a signed copy to the provided email addresses.
Applicants can request clarification using the Clarifications and Requests for Additional Information Template included in the RFQ document before 12 September 2023.
The SOQ and hard copy must be submitted by 14 October 2023.